Posted on: October 4, 2019

Old Troy/Bouse Road Update - Oct. 4, 2019

THESE ARE ANTICIPATED DATES ONLY.

Keller believes all main lane paving on Old Troy Road, Bouse, and the intersection will be completed by the 3rd week of October weather permitting. After that is complete, they will drop back and pour the east entrance of Fairfield early the 4th week of October. This would allow us to open the road to traffic by the end of October. The remaining entrances (the other half of Fairfield, Liberty Place, and Father McGivney) would be poured while the road is open to traffic.

The next pour Keller has scheduled is Tuesday, 10/8 weather permitting. They will pour the east bound lane of West Bouse from the far west end to where completed. Since Bouse road is so narrow, Keller will have to utilize the temp road to place the concrete. Traffic will be maintained by flaggers, but some congestion/delays should be expected.

THESE ARE ANTICIPATED DATES ONLY.

If you have any questions or concerns please contact Jennifer Doody, Public Works Director @ (618) 288-2647/jdoody@glen-carbon.il.us, Jamie Bowden, Village Administrator @ (618) 288-2614/jbowden@glen-carbon.il.us or Brian Kulick, Juneau Associates, Inc. @ 618-659-0900.


Facebook Twitter Email

Other News in Village of Glen Carbon Home Page

Large Item Pick Up

Posted on: October 8, 2019